Documented Findings

Surrey asked B.C.'s Inspector of Municipalities to investigate regional governance, pointing to a wastewater plant whose cost rose from $700 million to about $3.86 billion.

Summary

In 2026, Surrey city council unanimously passed a motion asking B.C.'s Inspector of Municipalities for a public inquiry into governance at the Metro Vancouver Regional District, citing financial stewardship concerns including the North Shore Wastewater Treatment Plant cost overrun.

On April 13, 2026, Surrey city council unanimously passed a motion requesting a public inquiry into governance at the Metro Vancouver Regional District and its related entities, CBC News reported. The motion, introduced by then-mayor Brenda Locke, asks B.C.’s Inspector of Municipalities to act and describes the regional body’s conduct as “unfairly oppressive” and “prejudicial.”

The motion came after council approved the city’s 2026 budget, which includes the tax Metro Vancouver levies on all ratepayers in the region. Locke told council Surrey was adopting the budget only because it was legally required to.

The wastewater overrun

Surrey’s concerns centre on Metro Vancouver’s financial stewardship, especially the North Shore Wastewater Treatment Plant. Its cost has grown from an original estimate of about $700 million to roughly $3.86 billion, and the overrun is shared across the region’s ratepayers, including Surrey residents.

Regional support and a separate lawsuit

By July 2026, New Westminster, the District of North Vancouver and the City of North Vancouver had each unanimously backed Surrey’s position, according to a statement from the City. Vancouver’s mayor also voiced support. The City says it has formally raised its concerns with the Province and continues to work with the Inspector of Municipalities.

Separately, Surrey has taken Metro Vancouver to court over its “Invest Vancouver” economic development service, alleging the regional district spent more than $16 million on it without the required approval. These are the City’s allegations and have not been decided by a court.

Why it matters

The City of Surrey says a large share of each property tax bill goes to other authorities, including Metro Vancouver, whose increases the city does not control. Regional cost overruns therefore reach Surrey taxpayers directly.

Unanswered questions

Has the Province responded to Surrey’s request? Will the new council continue to pursue the inquiry? How much of the wastewater overrun will Surrey ratepayers ultimately cover?

All information in this article comes from publicly available sources, linked below. Those named are invited to respond through our Right of Reply page, and any response will be added to this story.

Financial details

North Shore Wastewater Treatment Plant: from about $700 million (original estimate) to about $3.86 billion (as reported, 2026).

Official responses

No public response from Metro Vancouver or the Province found at time of writing.

Sources

  1. CBC News: Surrey seeking public inquiry into Metro Vancouver
  2. City of Surrey: Where do your property taxes really go
  3. City of Surrey: Growing support for Metro Vancouver inquiry
  4. Council minutes, April 13, 2026 (PDF)
  5. Global News: Surrey taking Metro Vancouver to court